Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the acf domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/wp-includes/functions.php on line 6121
Reading Hospital | Liberty Inc

Reading Hospital

Project Scope

Liberty Excavators is currently performing the site work for Reading Hospital’s extension of their existing 7th avenue building. This work consists of the removal and replacement of 6,600 LF of utilities, 1,220 LF of earth retention systems. These systems range in depths from 4’ to 38’ it also includes moving 140,000 CY of dirt off a 150,000 SF area.